Contacts / Technical Support
Solicitation Documents | Solicitation Schedule | Questions and Answers | Announcements

First New Jersey Offshore Wind Solicitation: Q&A

Questions submitted regarding the solicitation were collected, answered, and posted here by the BPU. Questions and answers posted are available for all to see. Please note that these answers are the opinion of Board Staff and should not be construed as opinions or rulings of the Board.

Questions were accepted until 6pm Tuesday, December 11, 2018.

RESPONSE:
All guidance, forms and applications to be used for this procurement are posted on www.njoffshorewind.com. All applicable requirements are stated within the Guidance Document. Please ensure PDFs are searchable and that the application is indexed so that information can be easily located.


RESPONSE:
The Solicitation Guidance Document specifies that bidders may offer projects up to 1,100 MW in size. The minimum offer size is 300 MW. Bidders may offer any size project within those parameters. However all bidders must offer at least one bid alternative sized bid at 400 MWs. In all instances these bid requirements refers to nameplate capacity. In general, Minimum bid size should be no more than 400 MWs of installed capacity but we will consider whatever you submit as the closest possible configuration based on the rated capacity of the selected turbine.


RESPONSE:
The Applicant should identify those State and Federal grants, rebates and tax credits which it is aware of, has considered, and has factored into the OREC Price. The Applicant should include documentation of these applications as may be available and "a description and estimate of any State or federal tax benefits that may be associated with the project" N.J.A.C. 14:8-6.5 (a) 3 and 5.


RESPONSE:
As noted in the Guidance Document (Section 3.18.2 Base/Alt Offer) if the bidder is electing to have their system upgrade cost estimate trued up to actual costs, they should indicate this on the sheet and show separately their "System Upgrade" costs. Note that even if the bidder is requesting this option, their All-in OREC Price should be inclusive of these System Upgrade costs and should provide the technical report used to estimate these costs at the time of the bid. The Applicant will be required to submit documentation to verify the actual "System Upgrade" costs such as the PJM Interconnection Report and cost estimate.  The OREC Price will be adjusted according to the difference in costs. If the verified costs are higher the OREC Price will be increased by the difference. If the verified costs are lower than what was estimated, the OREC Price will decrease by the difference.


RESPONSE:
Please see prior response to question regarding Changes to Employees.  The Board will review all requests made by the petitioner in a timely manner.  The petitioner may include in its request a time by when the decision is requested.


RESPONSE:
The website is structured in a manner that requires applicants to upload each section individually.  However an applicant may incorporate material from another section by reference to avoid redundancy.  The exception to this is the Environmental Protection Plan and Economic Development Plan which may reference other sections but must include each of the specified elements and should be comprehensive and detailed enough to provide a complete understanding how these plans shall be realized.


RESPONSE:
An applicant, as part of its application, may request a Waiver of certain administrative provisions under the OWEDA regulations and explain the reasons for the request, but expressly state that, in the event the Board denies the waiver request, the applicant would fully comply with the applicable Board regulations.  It is at the Board’s discretion whether to approve a request for a Waiver even if well supported.


RESPONSE:
The current solicitation does not include a surety bond or payment in the event an application is approved by the Board but the project contemplated thereby is delayed or is not ultimately constructed due to force majeure or otherwise.


RESPONSE:
An applicant is bound by all representations made in its Application to the State including those related to the project financing.  Any changes to the Project Financing Plan will be subject to Board Approval in order to ensure all risks are appropriately allocated and savings are passed along to ratepayers.


RESPONSE:
An applicant may propose to construct a single project in distinct phases, in which case each phase of the project may have an independent commencement of operations date based on the date the project is interconnected to the grid and the phase becomes operational.  In such a case each project phase may have differing 20 year OREC terms.  The OREC Pricing Plan for the project should include all project phases and should establish a uniform price for all ORECs generated in each Year.  An applicant may thus propose identical OREC Prices across multiple phases for any given energy year, even if such phases achieve COD in differing years. Thus if Phase 2 begins operation in Year 5 it should reflect the set OREC Price for Year 5 vs offering separate OREC Schedules.

The application form included as Attachment 1 to the Guidance Document has been adjusted to allow an applicant to propose OREC pricing beyond 2043.  Bidders are encouraged to use a separate pricing sheet per project phase and make it clear in their submission if the phases are a single offer – i.e. if the entire offer must be taken or if a single phase may also be accepted.


RESPONSE:
The OREC Application Form is meant to give the Board an “at a glance” summary of the project application.  In that context, the Levelized OREC price is intended to provide an average of the actual, nominal, fixed OREC prices New Jersey ratepayers will pay over the life of the project.  As such the Form works as intended.

We are concerned that including additional years of discounting for a project that has a later commercial operation date might be misleading when applied only to costs because the delay also means that New Jersey must wait to realize the economic and environmental benefits off the project.  We do expect all project applicants to calculate the benefits and costs of the project by discounting back to a common date; that will assure the effect of the later start date is reflected in both benefits and costs.


RESPONSE:
The Application Form is designed to provide a high-level overview of the project that is comparable across all projects.  As such, the output calculation is accurate for the purposes of the form.  Nonetheless, should bidders wish to fine tune their annual output estimate the relevant column has been unlocked to allow for such editing.


RESPONSE:
The time period on the revised Application Form has been extended through energy year 2050.


RESPONSE:
To align with the request above for a fixed price per energy year the revised Application Form has been adjusted to make it clear that each year represents an Energy Year.  Regarding partial year output, the Application Form is designed to provide a high-level overview of the project that is comparable across all projects.  As such, the output calculation is accurate for the purposes of the form.  Nonetheless, should bidders wish to fine tune their annual output estimate the relevant column has been unlocked to allow for such editing.


RESPONSE:
Per N.J.A.C. 14:8-6.5 (a).12.iii “[t]he Board requires a fixed, flat OREC price for the proposed term or a fixed price for every contract year.”  However, for the sake of alignment with existing and proposed processes regarding payment, true-ups, and OREC purchase requirements the Board would request that bidders asking for a non-levelized price provide a fixed price per energy year.  To be clear, the total OREC purchase term should cover a twenty-year period from COD and COD does not have to begin in June.


RESPONSE:
OWEDA and the implementing rules at N.J.A.C. 14:8-6 which govern the solicitation of 1,100 MWs only contemplate the procurement of a set amount of nameplate capacity as determined by the manufacturer of the selected turbine.  The BPU thus requests that all bidders use nameplate capacity in describing their respective capacity bids.  All production estimates should also be based on nameplate capacity minus any losses.


RESPONSE:
PJM defines seasonal peak and off-peak hours for both the wholesale energy market and for the capacity market.  PJM data is available here:  https://www.pjm.com/markets-and-operations/energy.aspx

Please note that PJM uses Locational Marginal Pricing (LMP) which is defined by PJM as “the marginal price for energy at the location where the energy is delivered or received. LMP is expressed in dollars per megawatt-hour ($/ MWh). LMP is a pricing approach that addresses Transmission System congestion and loss costs, as well as energy costs. Therefore, each spot market energy customer pays an energy price that includes the full marginal cost of delivering an increment of energy to the purchaser’s location.”

Also of note, New Jersey is within the EMAAC Locational Delivery Area (LDA) which represents the Eastern Mid-Atlantic Area Council (EMAAC) Region.

The PJM Market Monitor may also provide useful data and reports available at www.monitoringanalytics.com


RESPONSE:
The goal of the BPU is not to impede business operations but rather ensure that a comparable level of expertise and oversight represented by the Applicant is maintained during the course of operations. The BPU thus requests notification of changes in “key employees” who have been designated by the Applicant pursuant to the rules at N.J.A.C. 14:8-6.5 which state;

The Applicant shall, for the duration of the project, commit to: notifying the Board, within 30 days of the departure of any key employee; submitting the expertise and qualifications for any new key employee for approval by the Board; seeking Board approval for any changes to the organizational structure of key employee positions and the level of expertise and qualifications of those key employees; and obtaining prior Board approval of an entity to assume a controlling interest in the proposed project or the approved qualified offshore wind project.  Enforcement of this provision shall be a condition of the order granting ORECs. (N.J.A.C. 14:8-6.5)

The notification should include the reason for the change, when the change is to be effective, and the complete qualifications of the proposed new key employee.  Additional provisions will be spelled out in future rule amendments which will be subject to public comment.  The Applicant may however request a Waiver of these provisions if too restrictive and propose alternate provisions and timeline for notifications suitable to its business operations.  However, the Board is under no obligation to grant such a Waiver.


RESPONSE:
The Offshore wind developers are asked to report to the OREC Administrator and to the Board annually on actions taken by the developer to maximize offshore wind production and market revenues.  The Annual Offshore Wind Developer Report will be delivered to BPU Staff and filed with the Board on an annual basis within three months after the close of the energy year.  The Board shall review and accept the filing as complete or request additional information.   The primary intent is to ensure the revenues due to be refunded to ratepayers are being managed in the best interest of the ratepayer. Based on the Annual Offshore Wind Developer Report, The Board may ask questions, propose a course of action or propose a course of study.


RESPONSE:
Upon Board approval of an Annual OREC Schedule and the designation of a proposed project as “a qualified offshore wind facility,” The Board will then direct the EDCs to jointly contract the OREC Administrator.  The RFP and final contract award will be subject to Board Approval.  The contracted OREC Administrator will then draft the Standard Participation Agreement consistent with the rules at N.J.A.C. 14:8-6.5-7 and subject to Board Approval.  The OREC Participation Agreement cannot vary from the governing rules established under N.J.A.C. 14:8-6.6-7.   The OREC Participation Agreement will facilitate implementation of the rules by detailing the monthly invoicing, payments and accounting of all OREC revenues and OSW project revenues as well as the annual true-up of all obligations as described in the proposed OREC Funding Mechanism Rules.


RESPONSE:
The Board considers safety as a core responsibility of all ocean users across the entire offshore wind supply chain and throughout all stages of development and operation. However, the BPU does not regulate marine transportation in Federal Waters and thus must confer with federal agencies such as the U.S. Coast Guard and the Bureau of Ocean Energy Management (BOEM) on such requirements.  An OREC Award resulting from this solicitation process is contingent upon the applicant receiving all necessary state and federal permits and operating in compliance with those regulations. 

Federal and State Agencies including the BPU do however consider the type of issues raised in your comment through the BOEM Intergovernmental Taskforce in its deliberations to establish new offshore wind lease areas and the federal regulations that offshore wind lease holders are subject to in the building and operation of offshore wind facilities.  The BPU will confer with fellow Taskforce members as to how best integrate the recommended safety features. However, we encourage the Maritime Association to submit these comments directly to BOEM and the US Coast Guard for further deliberation.


RESPONSE:
See BPU Staff response regarding issues of ‘confidentiality’.

BPU Staff noted that this matter is considered a competitive solicitation and further noted that this matter will not be treated as a contested case with intervenors. Interested parties and stakeholders, including other applicants or potential applicants for QOWP status, will not therefore have standing to intervene or participate in QOWP application proceedings of other applicants.


RESPONSE:
The BPU appreciates the value of a competitive solicitation requiring a “sealed one-time bid” to help discover the most competitive pricing and has considered this format in other solicitations.  This type of format is most applicable to competitive solicitations where there is relative uniformity to bids and the products or services being offered as in the case of electric generation where all bidders offer $/MWh price for the generation and delivery of electricity.  However, in this current solicitation OWEDA and the governing rules at N.J.A.C. 14:8-6 require that the Board consider price ($/MWh) and other factors including broad “net economic and environmental benefits” associated with each project.  The BPU is seeking the lowest OREC Price ($/MWh) but also the “best value” for New Jersey ratepayers relative to the net economic benefits.   As noted above the Board thus reserves the right to negotiate the final OREC Price with any and all applicants in the best interest of the ratepayer.


RESPONSE:
The BPU appreciates the recommendation for consideration of floating offshore wind turbines. Applicants may choose any preferred technology based on its costs, site suitability and other benefits.  Floating offshore wind turbines however are generally  suitable to deeper waters further offshore than the federal lease areas being considered in this current solicitation.  However, future lease areas and solicitations may utilize this emerging technology which offers numerous benefits referenced above.


RESPONSE:
The BPU appreciates the confidential nature of some of the material that must be submitted with an application for a determination that a Project is a Qualified Offshore Wind Project (“QOWP”) pursuant to the requirements of N.J.A.C. 14:8-6.5 (the “Application Regulations”).  The Solicitation Guidance Document:  Guidelines for Application Submission for Proposed Offshore Wind Facilities asks applicants to identify any confidential information: “The bidder should identify any information that they wish to keep confidential.” (Page 7)

Furthermore, BPU Staff confirmed at the BPU Public Stakeholder Meeting on November 13, 2018, the that the Solicitation for 1,100 MWs of offshore wind capacity will be treated as a competitive solicitation whereby applications will be considered confidential in accordance with the Open Public Records Act, N.J.S.A. 47:1A-1 et seq. (OPRA) and the guidelines used by the State and all State Agencies for competitive solicitations (N.J.A.C. 17:12). Section  17:12-1.2 (b) and (c) on Public Information state:

(b) After the opening of sealed proposals, all information submitted by bidders in response to a solicitation of proposals is considered public information, notwithstanding any disclaimers to the contrary submitted by a bidder, except when an RFP contains a negotiation component or as may be exempted from public disclosure by the Open Public Records Act, N.J.S.A. 47:1A-1 et seq. (OPRA), and the common law. As a part of its proposal, each bidder may identify any data or materials it asserts are exempt from public disclosure under OPRA and/or the common law, explaining the basis for such assertion. Assertions that the entire proposal and/or prices are exempt from public disclosure under OPRA, the common law, or the U.S. Copyright Act are overbroad and will not be honored by the Division. In the event that a public request is made for materials that the bidder has identified as confidential, the Director [Board Secretary?] shall have the final authority to determine whether the materials are exempt from public disclosure under OPRA and shall take action as required by applicable law. The bidder or contractor may elect to defend its assertion of exemption from the public disclosure requirements of OPRA or the common law, but in doing so, all costs and expenses Page 3 of 32 associated therewith shall be the responsibility of the bidder or contractor. The State assumes no such responsibility or liability. (c) When the RFP permits negotiation with bidders after the submission of proposals, such proposals shall be made publicly available only after issuance of a notice of intent to award.

Since this matter is a competitive solicitation, BPU Staff further noted that this matter will not be treated as a contested case with intervenors. Interested parties and stakeholders, including other applicants or potential applicants for QOWP status, will not therefor have standing to intervene or participate in QOWP application proceedings of other applicants.

The BPU thus requests that an Applicant submit electronic copies of a public copy (redacted) of an application and confidential copy (un-redacted) through the website at www.NJOffshoreWind.com.  The Application should be accompanied by a Statement by the Applicant pertaining to the confidential nature of the application, identifying the type of data or materials it asserts are exempt from public disclosure under OPRA and/or the common law, and explaining the basis for such assertion. Assertions that the entire proposal and/or prices are exempt from public disclosure under OPRA, the common law, or the U.S. Copyright Act are overbroad and will not be honored by the Board.


RESPONSE:
The governing law and rules do not require a clearing price for ORECs and allow for individual OREC prices.  However, the Board reserves the right to negotiate the final OREC Price with any and all applicants in the best interest of the ratepayer.


RESPONSE:
OWEDA and the rules at N.J.A.C 14:8-6 do not provide for a screening process or pre-qualification to remove bids based on bid weaknesses that may be perceived as speculative. The governing law and rules require a determination of Administrative Completeness based on application requirements stipulated at N.J.A.C. 14:8-6 which require supporting documentation of all inputs and pricing tied to the OREC Price for the project to guard against speculative bids.  Furthermore, The Solicitation Guidance Document Section 4.0 Criteria for Evaluation of Applications  further states that “To be eligible to win a contract for the sale of ORECs, an Applicant must: “Demonstrate the project is viable it is likely to come on-line on time and on budget.”  The Criteria against which the project will be evaluated includes “Likelihood of successful commercial operation – This includes feasibility of project timelines, permitting plans, equipment and labor supply plans and the current progress displayed in achieving these plans.”  A speculative bid would not pass this threshold.


RESPONSE:
The question includes some legal opinions regarding the “merit order effect” which are not appropriate  to address here.  The valuation and contribution of the “merit order effect” is not requested as part of net economic benefits and ratepayer impacts within the Cost Benefit Analysis.  This potential benefit is not specific to offshore wind generation and is not being evaluated in this solicitation.   Moreover, price suppression is not among the goals of OWEDA and including price suppression benefits will raise red flags for Federal regulators and Federal courts.


RESPONSE:
The comparative bid evaluation for OREC Purchase Price (Criteria 1 in Section 4.0), Economic Impacts (Criteria 2 of Section 4.0) and Ratepayer Impacts (Criteria 3 in Section 4.0) will be based on P50 Production.  The Solicitation Guidance document requests at a minimum bids be presented based on a P50 production estimate.    Subsection 3.3 Financial Analysis (14:8:6.5.(a).3)requests bidders calculate the levelized cost of energy (LCOE) using P(50) output (Page 8).  Subsection 3.11 Cost Benefit Analysis (14:8:6.5. (a).11) also requests calculations based on a P(50) output .  Subsection 3.18 Application Form requests that bidders should specify, for each alternative [bid], the nameplate capacity of the project, turbine type, P(50) net capacity factor and location information as well as contact information. (Page 16).

Bidders are free to base their OREC purchase price off of another level of production, provided such price is appropriately tied to project costs.


RESPONSE:
Rate Impact will be evaluated based on total rate impact of the project $/kWh on Residential and Commercial Customers and based on rate impact per the installed capacity $/MW.


RESPONSE:
Without knowing which input/output models will be selected by the applicants and the assumptions/inputs to be used, the BPU cannot establish a calculation to normalize results.  However OWEDA and the rules at N.J.A.C. 14:8-6 specifically allows for the BPU and its economic consultant to test an applicant’s cost benefit analysis by inputting alternate assumptions or running the same assumptions through the model of the State’s choosing.  Furthermore, all assumptions used in the model must be documented and transparent so that the evaluation team can run its own analysis.

N.J.A.C. 14:8-6.5, 11 (x-xii) specifically states “The major assumptions and inputs used in the modeling must be specified by the applicant;  xi. The Board staff may ask the applicant to rerun the model with other assumptions and inputs to be provided by the Board staff; xii. The Board staff may test an applicant’s cost benefit analysis on its own model, which, preferably, would be the same one used by an applicant but it could be a different one, by replicating the analysis using model inputs supplied by the applicant;”


RESPONSE:
As noted in the Solicitation Guidance Document, “The Applications will be evaluated against the six criteria which reflect the goals of New Jersey’s OSW policy. The goals are: to promote economic development by jump-starting an OSW supply chain in the State; to combat the threat of global climate change to New Jersey; and to achieve these first two goals at the lowest reasonable cost and lowest risk to New Jersey ratepayers.”   Projects with lowest costs ($/MWh) and highest benefits ($/MW) and relatively low risk will do best.  The Board will make the final determination in accordance with OWEDA and the governing rules.


RESPONSE:
The Solicitation Guidance Document notes thatAn estimate of Transmission System Upgrade costs must also be included in the OREC Purchase Price along with documentation. While the BPU prefers a fixed price offer, they will entertain offers in which the OREC price is trued up based on the difference between estimated and actual system upgrade costs.”  This provision does not allow for a cost overrun.  It allows a developer who may not have completed the PJM interconnections process to submit an estimated cost that is fully supported and to then true up OREC price upon receipt of a final cost study from PJM.


RESPONSE:
The Definitions under OWEDA and the governing rules at N.J.A.C. 14:8-6 define a  Qualified offshore wind facility as follows:  “Qualified offshore wind project” means a wind turbine electric generation facility in the Atlantic Ocean and connected to the electrical transmission system in this State, and includes the associated transmission-related interconnection facilities and equipment, and approved by the Board pursuant to section 3 of P.L. 1999, c. 23 (N.J.S.A. 48:3-51).

In order to meet this definition of a “Qualified Offshore Wind Project” the project must interconnect within one of the four electric distribution companies operating in New Jersey and within the PJM Control Area in New Jersey which includes: Atlantic City Electric Company (ACE); Jersey Central Power and Light (JCP&L); Public Service Electric & Gas (PSE&G); Rockland Electric Company. (i.e. PJM Control Areas in New Jersey).


RESPONSE:
The Offshore Wind regulations require a bid that bundles OSW generation and transmission.  The rules governing the application and award of ORECs define a “Qualified offshore wind project” as “a wind turbine electric generation facility in the Atlantic Ocean and connected to the electrical transmission system in this State, and includes the associated transmission-related interconnection facilities and equipment, and approved by the Board pursuant to section 3 of  P.L.2010, c. 57 (C.48:3-87.1 ). (N.J.S.A. 48:3-51).”  The Application requirements  (N.J.A.C. 14:8-6.14) also specifically request an Interconnection Plan for how the project will interconnect to the grid, including the location of transmission lines and all points of interconnection to the PJM system serving New Jersey.   The OREC Price thus reflects the full cost of the offshore wind generation facility and the interconnection and should be considered as “a bid that bundles OSW generation and transmission.”   Applicants may partner with transmission providers to meet this requirement.

The BPU will consider offers in which NJ utilities or their affiliates participate.  The offer must disclose all participants and their relation to NJ utilities and explain how their project conforms with applicable laws.  The BPU retains the right to accept or reject all offers made into the RFP.


RESPONSE:
The Guidance Document requests $150,000 which is consistent with the rules that state a minimum amount and also allow for BPU to request additional funds as needed “based on the current and expected costs associated with the application review and related administrative proceedings.” (NJAC 14:8-6.5. (a). 15. Applicants should make payment in the amount of $150,000 consistent with the Guidance Document.  All checks should be made out to “Treasurer – State of New Jersey” and sent to the following address:

New Jersey Board of Public Utilities

Attn:  Chief Fiscal Officer

44 South Clinton Avenue, 9th Floor

P.O. Box 350

Trenton, NJ 08625-0350


RESPONSE:
The BPU is asking for how the offshore wind project may affect or address existing problems on the grid.  Specifically the rules require that the Interconnection Plan and application include “a detailed description of how the proposed project will address and mitigate load constraints in the electric distribution and PJM transmission system.” The Interconnection Plan must also “demonstrate to the greatest extent possible how the project will address current or potential future load pocket or constraint problems with the electric distribution system and the PJM transmission system.” (N.J.A.C. 14:8-6.14 (iii, iv)).


RESPONSE:
At present, the BPU does not intend to solicit interconnection cost studies from 3rd parties to compare interconnection costs.  The BPU also does not intend to open a subsequent transmission only solicitation before an award is made for this first solicitation of 1,100 MWs. The BPU also has no plan to “assign on shore portion of interconnection to incumbent utility in order to leverage existing infrastructure.”  The BPU reserves the right to examine interconnection costs and to consider cost reduction measures that may be available or not considered by the applicant.


RESPONSE:
The Applicant is responsible for preparing a bid that is in conformance with all Application Requirements specified under N.J.A.C 14:8-6 and the Guidance Document.  Once an Application is deemed Administratively Complete, the BPU and evaluation team may request additional clarifying information, to which the applicant may respond, however the responsibility rests with the applicant to conform to all specified requirements.  The BPU may also negotiate the final price and other elements of the application in order to make a final award.


RESPONSE:
The OREC Price includes the cost of transmission and interconnection costs per the requirements established under OWEDA and at N.J.A.C 14:8-6.  However, only on-shore system upgrade costs are eligible for a true-up.  Direct interconnection costs are not eligible for true-up (but must be split out somewhere in your offer). Please reference the following definitions:

  1. “System upgrade costs” includes the on-shore transmission owner upgrades necessitated by the OSW interconnection request.
  2. “Direct interconnection costs” includes the off-shore substation and all associated facilities up to the transmission owners point of interconnection

RESPONSE:
The Application Form only requests the separation of system upgrade costs because those are the only costs eligible for true-up (at bidders request).  Direct Interconnection costs may be identified in the Financial Analysis and the OREC Pricing Schedule.


RESPONSE:
The OREC Price includes the cost of transmission and interconnection costs per the requirements established under OWEDA and at N.J.A.C 14:8-6.  However, only on-shore system upgrade costs are eligible for a true-up.  Direct interconnection costs are not eligible for true-up (but must be split out somewhere in your offer). Please reference the following definitions:

  1. “System upgrade costs” includes the on-shore transmission owner upgrades necessitated by the OSW interconnection request.
  2. “Direct interconnection costs” includes the off-shore substation and all associated facilities up to the transmission owners point of interconnection

RESPONSE:
The OREC Price includes the cost of transmission and interconnection costs per the requirements established under OWEDA and at N.J.A.C 14:8-6.  However, only on-shore system upgrade costs are eligible for a true-up.  Direct interconnection costs are not eligible for true-up (but must be split out somewhere in your offer). Please reference the following definitions:

  1. “System upgrade costs” includes the on-shore transmission owner upgrades necessitated by the OSW interconnection request.
  2. “Direct interconnection costs” includes the off-shore substation and all associated facilities up to the transmission owners point of interconnection

RESPONSE:
The OREC Price includes the cost of transmission and interconnection costs per the requirements established under OWEDA and at N.J.A.C 14:8-6.  However, only on-shore system upgrade costs are eligible for a true-up.  Direct interconnection costs are not eligible for true-up (but must be split out somewhere in your offer). Please reference the following definitions:

  1. “System upgrade costs” includes the on-shore transmission owner upgrades necessitated by the OSW interconnection request.
  2. “Direct interconnection costs” includes the off-shore substation and all associated facilities up to the transmission owners point of interconnection

RESPONSE:
The OREC Price includes the cost of transmission and interconnection costs per the requirements established under OWEDA and at N.J.A.C 14:8-6.  However, only on-shore system upgrade costs are eligible for a true-up.  Direct interconnection costs are not eligible for true-up (but must be split out somewhere in your offer). Please reference the following definitions:

  1. “System upgrade costs” includes the on-shore transmission owner upgrades necessitated by the OSW interconnection request.
  2. “Direct interconnection costs” includes the off-shore substation and all associated facilities up to the transmission owners point of interconnection